Study Schedule
The study is scheduled to span 16 months and is broken down into the following four phases:
Study Initiation (Sept, 2010 - Jan, 2011)
- Mobilize team and administer the study
- Develop Purpose and Need statement
- Initiate public outreach
- Collect and assess data and information
- Build models and tools
- Travel models, econ impacts models, WEBOT
Initial Development and Evaluation of Concepts (Nov, 2010 - April, 2011)
- Develop evaluation criteria and MOEs
- Define range of concepts for consideration
- Work with committees to develop and refine
- Evaluate concepts (key MOEs)
- Recommend and select concepts for further refinement and evaluation
Detailed Screening and Evaluation of Strategies (March, 2011 - August, 2011)
- Refine evaluation criteria and MOEs
- Develop packages of complementary strategies for detailed evaluation
- Detailed evaluation of strategy packages
- Modeling
- Account for potential economic development affects
- Select and prioritize recommendations
Study Finalization (Aug, 2011 - Jan, 2012)
- Document study process
- Public review and comment of study report